September 2024
See photos below.
August 2024
See photos below.
July 2024
See photos below.
June 2024
Horizontal construction to resume the first week of July with the first lots to deliver in the 1st quarter of 2025. We have been working to get everything in place and permits in order for horizontal construction to continue. While we were waiting for those, we pushed forward quickly with phase 1 and with that being close to completion, we are ready to get horizontal construction moving on phase 2 in July. We are anticipating being able to deliver the 1st lots in Q1 of 2025.
April 2024
Horizontal Construction is complete (Grading 95%, Storm 100%, Sewer 100% and Water 100%) for Columbus Creek. The curb is installed and throats and tops are mostly complete. Binder is down and site contractor is looking to turnover the site to the vertical GC . Subdivision Plat has been approved and each building has its own address.
March 2024
The mass grading is complete for Covington Creek 2, we appear to have reached the end of our Rock issues and are working to bring the pads to final grade. The installation of retaining walls and storm is complete and the work in the ROW is underway.
February 2024
February has been very wet and in turn very slow progress for Covington Creek 2. The right of way work is underway and the mass grading is complete. We appear to have reached the end of our Rock issues and are working to bring the pads to final grade. The installation of retaining walls and storm is complete and the work in the ROW is underway.
January 2024
January has been very wet and in turn very slow progress for CC2. The right of way work is underway for Covington Creek 2. The mass grading is complete fand we appear to have reached the end of our Rock issues. We are working to bring the pads to final grade. The installation of retaining walls and storm is complete and the work in the ROW is underway. The bore pits, jack and bore and sewer taps were completed in December.
Want to look back? Follow the link to see past progress updates from previous years. VIEW