Verde Commons

Scroll through to see all past monthly updates.

October 2024

Gas work is nearly complete, with paving to follow. Interior work on the homes continues, including painting, flooring, and carpentry. We have signed an agreement with a real estate group who will assist in selling the units as well as manage them for those who want to rent.


September 2024

All homes are now fully framed and have siding installed. Many of the homes already have drywall installed, and trim is being delivered now, bringing us one step closer to completion! Mid-November is when we expect our first homes to be ready for their new owners. Plus, the road paving is set to kick off at the end of October, following the completion of final gas work, ensuring smooth access to this fantastic neighborhood.


August 2024

Work is progressing well. All 13 houses are framed and roofed in. Seven of them have siding work complete with work started on another. The remaining 5 are being wrapped in.


July 2024

Utility work is complete, and each home is framed! Some units already have siding completed. We are on schedule to have the first homes completed by September.


June 2024

Progress continues to move quickly as 9 of the 13 buildings are in various stages of vertical construction. 8 are completely framed and 9th is close to being framed. The first home has been dried in with siding almost complete and they are working on drying in the second. HVAC, plumbers, and electricians are working together to get started on the inside of the buildings. Our builder is finishing up the final subdivision permits for drainage improvements and pond installation. Professional designers have selected colors and finishes for the homes.


May 2024

Underground utility work has been completed, and vertical construction has started! Two of the 13 buildings have nearly completed their framing stages, with three others in progress.


February 2024

New driveway aprons have been installed at the three entrances to the community that will provide ADA access to the community. Building permits have been issued, and framing is expected to begin shortly after utility connections are completed.


January 2024

We are waiting on building permits to be issued before we begin vertical construction.

Want to look back? Follow the link to see past progress updates from previous years. VIEW